SINGAPORE: SBS Transit Limited has been appointed the new operator for Downtown Line, Singapore's fifth Mass Rapid Transit line.
When completed by 2017, the Downtown Line's 34 stations are expected to serve about half a million commuters daily.
The
Land Transport Authority (LTA) says the Downtown Line is the first rail
line put up for competitive tender under the new rail financing
framework LTA adopted in 2010.
Among other things, the licence
period for the appointed operator is shorter - about 15 years, down from
the existing 30 to 40 years.
And the LTA will own the rail operating assets and be responsible for timely replacements and enhancements.
In
the case of the Downtown Line, the licence period is about 15 years
from full completion in 2017, a few years after Downtown Line Stage
One's targeted opening in 2013.
The LTA says the shorter
duration will encourage efficiency through competition, as other
operators may bid at the end of the licence term.
The appointed Downtown Line operator, SBS Transit Limited, will pay an annual licence charge over a 19-year licence period.
This payment is expected to reach an estimated total of S$1.6 billion at the end of the 19 years.
The payment will be placed in a Railway Sinking Fund to be managed by LTA to meet future expenditures on operating assets.
The
LTA says the two local public transport operators, SBS Transit Limited
and SMRT Trains Limited, both submitted competitive proposals to operate
the Downtown Line.
It says SBS Transit Limited was picked after careful consideration.
SBS Transit is about 75 percent-owned by Singapore's biggest bus and taxi operator, ComfortDelGro.
The Downtown Line project was announced in 2005. It was later described as a major challenge.
LTA's
project engineer, Darren Lau, had said: "The Downtown Line is currently
one of the most challenging rail projects in Singapore, as it passes
through varied soil conditions along the stretch. In certain areas like
Bukit Timah, we even had to resort to using explosives to break up the
granite rocks."
The Downtown Line was initially a five-station
extension to the Circle Line. Known as Downtown Extension - running
between Millenia Station and ending at Chinatown Station on the North
East Line - it was expected to cost some S$1.4 billion and be completed
by 2012.
But in 2007, the government approved S$12 billion worth
of plans to add more than 40 kilometres to the existing mass rapid
system.
The aim is to raise the number of those commuting by public transport to 70 per cent by 2020.
The Downtown Line will now have 34 stations in all - constructed over three phases.
Stage One involved the stations of the original Downtown Extension, running 4.3 kilometres from Chinatown to Bugis.
Work on Stage Two started in 2009, covering 12 underground stations over 16.6 kilometres.
When
completed in 2015, Downtown Line 2 will run from Bukit Panjang, along
the Bukit Timah Corridor and terminate at Rochor Station, where
passengers can connect at Bugis.
The final 21-kilometre stretch
of Downtown Line 3 will link the Singapore EXPO Convention and
Exhibition Centre in the east to Bukit Panjang, with a loop through
Marina Bay.
Personal View: This will more or less cause a upswing for the stock ComfortDelGro, do keep a lookout for it.
No comments:
Post a Comment